Major refurbishment of a five storey office block including a new Mechanical & Electrical package, decoration, flooring and new kitchens. The phased refurbishment incorporated:
- Removal and erection of internal walls
- Floor covering replacement
- Redecoration
- Installation of new kitchens
- Modification of existing power, data and lighting installations
Midland House proved to be a challenging project, having to re-house up to 300 individuals as each floor was refurbished. This required regular meetings and close liaison with council leaders to ensure smooth operational handover of sectional completed areas.
Each floor was remodeled, incorporating new offices, secure interview rooms and kitchen/canteen areas for the staff.
The project was delivered on time and to the contract sum, through careful management, much to the satisfaction of the local council.
Information:
- Office refurbishment
- Client – Plymouth City Council
- Completion – March 2012
- Value – £317,000