Stoke Damerel Primary School, Plymouth

A basic needs project comprising the construction of four extensions to the existing school – providing new classroom spaces and additional WC facilities – and internal refurbishment to a number of rooms.  External works included the creation of new playground areas.

The project was phased to ensure minimum effect on the smooth running of the school.  Phase 1) modify and refurbish existing teaching and staff room spaces Phase 2) construction of the extensions.

The project was completed to budget, on time and to the satisfaction of the client.  Ryearch received very strong feedback on the Performance Assessment Questionnaire, which is given to each client when their project has been completed.

Information:

  • Primary School extension
  • Client – Plymouth City Council
  • Completion – February 2013
  • Value – £505,000